000 03091ntm a2200373 i 4500
999 _c92510
_d92516
003 MY-KuUP
005 20251125105549.0
006 t||||fr|||| 000 0
007 ta
008 200707t20192019my a|||fram|| 000 0 eng d
020 _aTHE0008705(Local)
_qhardback
040 _aUMP
_beng
_cUMP
_erda
090 _aFKASA .H35 2019 r Bc.
100 0 _aNur Haisera Idris,
_eauthor.
245 1 0 _aExploring risk associated to public infrastructure projects case study of Kuala Terengganu by pass /
_cNur Haisera Idris
264 1 _aKuantan, Pahang :
_bUMP,
_c2019
264 4 _c© 2019
300 _aix, 38 pages :
_billustrations ;
_c30 cm. +
_e1 CD-ROM
336 _atext
_2rdacontent
336 _atext
_2rdacontent
337 _aunmediated
_2rdamedia
337 _acomputer
_2rdamedia
338 _avolume
_2rdacarrier
338 _acomputer disc
_2rdacarrier
347 _atext file
_bPDF
_2rda
500 _aFaculty of Civil Engineering and Earth Resources
502 _aProject Paper (Bachelors of Civil Engineering) -- Universiti Malaysia Pahang – 2019
504 _aIncludes bibliographical references
520 3 _aThis study proposed an empirical study of risk assessment module for public road construction projects. This study employs a case study of a conventional road construction projects for Bypass Kuala Terengganu that has been initiated by the Ministry of Works Malaysia since July 2016. The projects involve the construction of 5.875km route from the state route Tok Molor, Jalan Tok Adis (T12) to Kampng Durian Burung at Federal route (FT03) Kota Bharu-Kuala Terengganu. Seven delay factors and twenty-two sub-factors were designated from a review of literature and consultations with public road experts. The designate pair-wise questionnaire survey was distributed to the road project team in accordance with the Analytic Hierarchy Process (AHP) technique. The delay risk was assessed quantitatively by prioritizing the risk delay factors in determining the critical construction phase. This study identified the top five most prioritized factors as follows: that the most prioritised risk factor in infrastructure projects with respect to goal is technical risk (0.11029), followed by environmental risk (0.23276), project risk (0.34834), and operational is (0.30861). The sub-factors weights were also ranked and the top five sub-factors will be further discussed. The table 4 shows uncertainty of weather (0.73289) as the top risk which is the main caused most of the delay project, followed by land acquisition issues (0.55465), late submission of approved for construction drawing causing delay in in project submission delay (0.39605), the new design does not consider existing drainage system causing flood (0.35202), and unexpected ground condition (0.30084). Therefore, the AHP method can be identified by classification weighted of the most prioritize risk in this project.
610 2 0 _aFaculty of Civil Engineering and Earth Resources
_xDisertations
650 0 _aUniversities and colleges
_xDisertations
650 0 _aTheses
942 _2lcc
_cPSM